MPs issue ultimatum over Tochi irrigation scheme

Tochi Irrigation Scheme

The Parliamentary Committee on Agriculture, Animal Industry and Fisheries has given two weeks to over seven different sub-committees to provide a positive and comprehensive report on the Tochi Irrigation Scheme.

The committee has begun hearing the petition that was tabled before the Parliament of Uganda on September 30, 2026, by Oyam North MP, Dr. Eunice Apio Otuko, over the mismanagement of the Tochi Irrigation Scheme in Acaba sub-county, Oyam district.

Other concerned residents and beneficiaries were seated in the parliamentary gallery to witness the presentation.

The petition, signed by 25 representatives, highlights underutilization, incomplete infrastructure, and alleged corruption in the shs 45 billion government project that was meant to benefit 1,200 farmers but is currently benefiting only 52 farmers.

Immediately after receiving the petition, Jackson Oboth Oboth referred it to the Parliamentary Committee on Agriculture, giving the committee 30 days to investigate and report back to Parliament.

On Friday, November 21, 2026, the committee, chaired by Anne Amelia Kyambadde, invited the cooperative of the Tochi Irrigation Scheme in Oyam to investigate the matters alleged in the petition—that the government had invested over shs 45 billion to benefit a total of 1,200 farmers from the allocated areas, yet the committee has learned that only 52 farmers are the right beneficiaries of the project.

Another matter raised was that the farmers were not trained to operate and maintain the scheme, and it was also indicated that scheme officials were extorting money from farmers.

She added that it has been observed that there is no proper management of the Tochi project, while there was also insufficient data on the farmers because they do not know how many the right farmers are, as the list presented to them cannot provide the right figures of the beneficiaries.

Amelia noted that the scheme is operating without local leadership at the district level regarding what takes place at the cooperative.

After witnessing that there is no value for the shs 45 billion that was meant for irrigation, she said, “For that matter, we need a special auditor over the Tochi Irrigation Scheme.”

Oyam North MP, Dr. Eunice Apio Otuko, who tabled the matter before Parliament, said the main purpose of coming is to get the right information from the beneficiaries, who have alleged that there is too much corruption by the current leaders of Tochi.

She continued that, as leaders, they are being objective and not intending to cause any risk between members of the communities.

Dr. Apio appealed to the farmers to ensure that once they are out of the facility, they should not take it so negatively as to fight one another, and they should avoid segregation to help in investigating the issue and ensure that things are done.

Lugoloobi Willy B., MP for Bujumba County in Kalangala district, tasked CAO Oyam, Alex Felix Majeme, to explain his experience and also compare both Duca Cooperative in Butaleja and the Tochi Irrigation Scheme in Oyam to determine if there is any value for money.

He also wants the CAO to explain who always determines the amount of money to be paid by the farmers.

Kirungi Aneet Pamela, Woman Member of Parliament for Kabarole district, appreciated the people of Oyam for having this big project worth shs 45 billion, and appreciated President Yoweri Museveni Kaguta for considering this scheme and investing in it.

Also read: Irrigation technology, the only remedy to curb adverse effects of climate change on agriculture

However, she also disagreed with the CAO report, which indicates that out of 1,200 plots, only 294 farmers are in use, leaving a total of 906 plots out, although there have been interventions planned by the district.

She emphasised the percentage dropping from 46% at the beginning to 20%, saying this is not fair and a clear recommendation is needed on the entire project.

While presenting his report, chief petitioner and former Oyam South MP, Ishaa Otto Amiza, accused the Ministry of Water and Environment of implementing this project in a way that bypassed the district leadership.

He said the ministry went ahead and did the construction work under the central ministry with very little engagement and cooperation with the district leadership, and this is a big challenge that the ministry has created.

Otoo also rejected the report from the CAO that only shs 38 billion was invested in this project. He explained to the committee that documents from the Ministry of Water and Environment about the Tochi Irrigation Scheme show a total of shs 45 billion, but according to the district report, it does not reflect the right figures of money.

He lamented that this money also came with guidelines such as the construction of 10 dam ponds for fishing, construction of a 35km surrounding road near the scheme, a processing plant, full electricity power, and infrastructure as part of the project.

Tochi Irrigation Scheme

While delivering his report, CAO Oyam Alex Felix Majeme stated that the construction of the project started in 2017 under the Farm Income Enhancement and Forestry Conservation Program Phase II, financed by the African Development Bank and the Government of Uganda.

The Ministry of Water and Environment led the implementation of development activities, which continued through 2023 and were undertaken in two phases.

According to unconfirmed sources, the project cost about shs 38 billion, and that is what the report got since he was posted to Oyam four months ago, CAO Alex Felix Majeme stated.

He finally said the scheme was conceived to improve agricultural production and farm incomes through more reliable water access while contributing to food security, agribusiness development, climate resilience, and sustainable natural resource management.

He noted that the project had three wider components, which include distribution canals, drainage channels, access roads, and organised farming blocks.

Immediately, the committee chair formed over seven different sub-committees and gave them two weeks to submit their basic reports on the Tochi Irrigation Scheme.

These include the CAO committee, RDC committee, production committee, DISO report, water DPC, and LC5, which are to provide a comprehensive report within 14 days.


Discover more from tndNews, Uganda

Subscribe to get the latest posts sent to your email.

Leave your thoughts

Kindly write to us to copy and paste this article. Thank you!

Discover more from tndNews, Uganda

Subscribe now to keep reading and get access to the full archive.

Continue reading