MPs grill science ministry officials over shs5.5b innovation grant on a ghost project

innovation grant

Members of Parliament on the Science, Technology, and Innovation Committee on Friday grilled officials from the Ministry of Science, Technology, and Innovation over a shs5.5 billion grant awarded to Great Lakes Company for value-addition coffee innovation project.

Trouble began on Thursday, November 19, 2026, when the project supervisor, Isiko John, failed to tell the committee the location of the company.

This came after the committee chairperson, Dr Opio Samuel Acuti, raised concerns about the report presented by the Science, Technology, and Innovation Secretariat under the Office of the President

A phone number given to the committee in the report was unfortunately unavailable, while the location of the facility could not be traced. The known location of the facility in Ntinda Industrial Area, which the committee had visited a week earlier, was closed.

Locals nearby indicated that the facility had last operated more than three years ago.

The project supervisor, Joshua Isiko, however, indicated in his report that the facility was operational.

When questioned on the location of the facility for which he received over shs5.5 billion, he immediately failed to provide a relevant answer.

Further efforts to avail an alternative contact for the proprietor proved futile.

He later told the committee that the factory was in Kololo. However, on further questioning, he could not describe its location, which he claimed was near the Kololo airstrip.

The location he later described turned out to be a coffee shop, as noted by the Deputy Chair of the Committee, Prof. Willy Lubega.

According to Ministry documents, the venture leader for the project is Andreas Nicolaides, a foreign national of European origin. The project was expected to develop a long-shelf-life, ready-to-drink coffee.

The Ministry report indicated that the project was operational, producing 1.2 tonnes of roasted coffee per day, which were being exported, with five products certified by UNBS and on the market shelves.

Isiko, however, failed to trace the shops and supermarkets where the products were distributed, despite having superintended the project.

Great Lakes Coffee Ltd is reported to have received shs5.5 billion in the 2024/25 Financial Year.

However, various media sources indicate that the company went into receivership in 2023 following creditor action, including by Bank of Africa, with Kaibito Karamagi, Managing Partner at Ligomarc Advocates, and Rita Baguma Birungi appointed as receivers.

By 2024, the receivers had put the company’s assets on the market, prompting disputes over machinery, premises, and the legality of the receivership, which was challenged in the High Court under Civil Suit No. 0120 of 2024.

Innovation project

KCB Bank Uganda Limited also pursued the recovery of roughly USD 1.1 million (Civil Suit No. 0261 of 2024) against the company and shareholders/guarantors Andreas Nicolaides and Stamos Konstatinos, based on personal guarantees executed in July 2022.

Members of the committee were left questioning how shs5.5 billion was released to a company that had already ceased operations.


Discover more from tndNews, Uganda

Subscribe to get the latest posts sent to your email.

Leave your thoughts

Kindly write to us to copy and paste this article. Thank you!

Discover more from tndNews, Uganda

Subscribe now to keep reading and get access to the full archive.

Continue reading